Dupont's Construction Crews Reach the 1700 Block Just as the Holiday Season Starts

The big round hole in the middle of the new Dupont Circle deckover is meant to be there. It is 50 feet across, and it's the ventilation vent for the Connecticut Avenue tunnel below. Concrete barriers and a mounted rail surround it. DDOT explained it in its October 14 update, right after crews finished the fifth and last concrete pour on the deck.

By this week, the deck has moved on to the next stage. In its November 6 construction update, DDOT reported that pavers, the stones people will eventually walk on across the plaza, are now going down over the cured concrete. The same update said outreach had started with businesses on the 1700 block, where work is expected to begin "on or about November 23."

That timing shapes the neighborhood's holiday season. Most of the season's draws sit on blocks the crews have already finished or never worked on. The construction moves north onto one of Connecticut Avenue's busiest blocks for restaurants and shops at the start of the busiest shopping weeks of the year.

Where the work stands, block by block

The project runs in phases up Connecticut Avenue, and each block is at a different stage this week. Here's where things stood in DDOT's most recent updates.

Stretch Status in DDOT's latest updates
Deckover over the underpass All five concrete pours finished by mid-October; paver installation underway as of Nov. 6
1500 block, west side Service lane and sidewalk work continuing
1600 block, east side Close to finished; pavers in from the post office to R Street, service-lane traffic back as of Nov. 2
R Street and Connecticut intersection Crews finishing work here, along with new traffic signal and sidewalk work
1700 block Work expected to begin on or about Nov. 23
1800 block The separate Geneva residential conversion project is underway

The work covers more than paving. DDOT describes new traffic signals, new streetlights, and the electrical upgrades they need, plus stormwater upgrades and new sidewalks. Some of the work reaches a few yards down the side streets. On Q Street, just east of Connecticut, the work so far has meant new pavers, updated curb cuts, and new accessible ramps.

The 1800 block matters for anyone who lives or works north of R Street. DDOT notes that construction on the Geneva, a residential conversion, is going on in that block, and that the two project teams meet regularly to limit the effect on traffic and the community. Once the streetscape crews reach the 1700 block, that stretch will have active construction on its south end and work underway on the block just north of it.

The 1700 block is next

DDOT called out La Tomate Bistro, at 1701 Connecticut Ave NW at the tip of the block, as "the neighborhood's beloved La Tomate Bistro," and noted that "many other local businesses" share the block. The Dupont Circle BID's dining directory and shopping directory list these businesses on the block, among others:

  • Places to eat and drink: La Tomate Italian Bistro at 1701, Dolcezza Artisanal Gelato at 1704, Thai Chef at 1712, Rosemarino D'Italia at 1714, Bon Beke's Bakehouse & Grill at 1718, Tatiana Pizza at 1730, Viet Kitchen at 1732, Board Room at 1737, and Bistrot du Coin at 1738
  • Shops: Spirits & Spice at 1700, Secondi at 1702, Bloom at 1719, Bite the Fruit at 1723, The Newsroom at 1728, and Looped Yarn Works at 1732
  • Galleries and services: Vika Gallery on the lower level of 1700, with its entrance on R Street; Dupont Barber & Spa and Dupont Nails & Spa at 1706; and Cry Baby Studios and Jilly's Pilates at 1710

DDOT's November 6 update closed its note on the block with "More to come on the work in this block." The 1600 block, a block south, shows what a streetscape phase has looked like so far. Crews took out the old sidewalk, then put in new concrete, pavers, planters, and other infrastructure. While they worked, foot traffic moved to a protected walkway along the outer edge of the street, with ramps up to the shop entrances. DDOT's September 26 update put it plainly: "All businesses are open and accessible throughout the construction project." The project's general rules call for keeping access to businesses open, allow temporary pedestrian detours, and keep at least one traffic lane open in work zones.

DDOT also offered a suggestion of its own. Its October 7 update counted down the days to Hanukkah, Christmas, and Kwanzaa, then said: "Shopping at your local business, particularly those that have construction surrounding them, might be a good way to start marking off your shopping list while supporting our local neighborhood." For the rest of the season, the 1700 block is the block that suggestion fits best.

The holiday calendar sits on the quieter spokes

Most of this season's events are a block or more away from the work zone, on streets that come off the circle in other directions.

The DC Holiday Market has been open since November 12 on the 1500 block of New Hampshire Avenue NW. That stretch between Q Street and the circle is closed to cars for the market. According to the market's site, more than 35 small businesses are selling artisan goods, handmade products, and gifts there through Wednesday, December 23. Hours are noon to 8 p.m. on weekdays and 11 a.m. to 8 p.m. on weekends. It's closed on Thanksgiving Day, November 26, and on Monday, November 30, when exhibitors change over. The organizers mention Kramers Books & Café, Rokuya, The Pembroke, and the Dupont Circle Hotel as neighbors a few steps away.

FRESHFARM's Dupont Circle Farmers Market runs on Sundays at 1913 Massachusetts Avenue NW from 8:30 a.m. to 1:30 p.m. The BID lists dates of November 22 and 29 and December 6, 13, and 20.

The Trumpeter, an immersive theater production, is playing at Dupont Underground, 19 Dupont Circle NW. The BID's event listing shows performances through Sunday, November 22. That puts the last weekend of the show in the space beneath the circle on the weekend before the crews are expected to reach the 1700 block.

Heurich House Museum's Christmas Markt fills the museum's Castle Garden with local makers from Thursday, December 3, through Sunday, December 6. Details are on the museum's site.

The circle itself has already had its own repairs. The National Park Service wrote about its tradespeople restoring Dupont Circle. The work included about 10,000 feet of new bench slats, repairs to the fountain's pipes, and repairs to the stone and marble. NPS says the work got water moving in the fountain again. So the park in the middle of the circle has been restored, while the edges along Connecticut Avenue are still being rebuilt.

A 50th anniversary, a farewell, and a newcomer

Two long-running businesses mark this season.

Kramers, at 1517 Connecticut Ave NW, sits on a block where the deckover and service-lane work has been underway all fall. In October it marked 50 years in business. DDOT took time out of its October 21 construction update to congratulate the store, calling it "a true staple in the Dupont Circle community." So the store reached 50 with the construction just outside its door.

Floriana, at 1602 17th Street NW, is leaving after 47 years. PoPville reported the restaurant's announcement that its last night of service on 17th Street will be December 31, 2026, as it gets ready for "a new chapter in Old Town Alexandria, VA." The announcement also invites diners to "Dine with us through December 31." That leaves about six weeks of dinners at the 17th Street location, all during the holiday season.

The newer arrivals are opening on blocks the crews have already finished. PoPville reported that Pure Green is open at 1605 Connecticut Ave NW, in the space Zeleno used to occupy. It sits on the 1600 block, where the new sidewalk is close to finished.

Following the work week by week

DDOT posts its construction updates every Wednesday on the Connecticut Avenue Streetscape and Deckover project page. Questions go to the project team at [email protected]. DDOT has also pointed readers to Dupont Circle Main Streets on X and the Dupont Circle BID on Instagram for news about neighborhood events. In October, DDOT said it would brief ANC 2B on the project's progress at the commission's monthly meeting.

In its September 17 update, DDOT said the whole project was on schedule to finish in early summer 2027, subject to weather and unforeseen circumstances. That means the 1700 block's holiday season will likely be the last one this stretch of Connecticut Avenue spends under construction before the plaza opens.

Wondering what the deckover and the new streetscape could mean for your building or block once the plaza opens? Bobby Pichtel follows Dupont Circle block by block and can walk you through it. Get a free home valuation or start your DMV search. Contact Bobby today.

Work With Bobby

Bobby is dedicated to helping you find your dream home and assisting with any selling needs you may have. Contact Bobby today to start your home searching journey!

Follow Me on Instagram